On December 20th, 2013, the reporter learned from the Key Project Management Office of Kaifeng City, Henan Province that since 2013, the construction of the Xinwei automobile parts production project has progressed smoothly. By the end of November, the accumulated investment has reached 87.2 million yuan, accounting for the annual investment. 116.11% of the target mission is currently trial production.

It is reported that Xinwei Automobile Parts Production Project plans to invest a total of 14.51 million yuan, started construction in June 2012, and is scheduled to be completed and put into operation by the end of 2013. After the project is completed and put into production, the project will have an annual production capacity of 200,000 sets of trucks, minicars, and stampings. At present, the construction of the two factories of the project has been completed and trial production has started.

In the first 11 months, Henan Ruiyang Automobile Body Production Project has completed a total investment of 102 million yuan, accounting for 102% of the annual investment target task, and it is currently starting trial production.

It is reported that the total investment of Henan Ruiyang Body Production Project is 160 million yuan. Construction started in August 2012 and it is planned to be completed and put into operation by the end of 2014. After full completion and production, the project will have an annual production capacity of 60,000 tractor cabs. At present, the project plant construction is basically completed, the production line has been installed, and trial production has started.

52mm Neck Size Jar Preform

52Mm Neck Size Jar Preform,52Mm Pet Preform,52Mm Bottle Preform,52Mm Neck Pet Preform

Heshan Yecheng Plastic Products Co.,Ltd. , https://www.plasticpreform.com