At present, modern intelligent parking systems are widely used in various parking lots, underground garages, communities, and the gates of units. The main components of intelligent parking lots are: the system consists of entrance control machines, exit control machines, automatic barriers, and vehicles. Detector, communication converter, management software, full-scale display, charge display, issuer, image capture card, camera, proximity card and other components.

With the continuous development of the parking lot and the widespread use of parking lots, how to construct and wire the parking lot system has become a major problem for most of the newly-built parking lot project providers. Here we will help you solve this problem. The main configuration of the parking lot is: the system consists of entrance control machines, exit control machines, automatic barriers, vehicle detectors, communication converters, management software, full-scale display screens, charging display screens, issuance machines, and image capture cards. Camera, proximity card and other components. With the technical requirements of new technologies and new products developed by security technology, in line with the needs of customers and the first purpose of users, the following project construction specifications are formulated.

I. Main material and tool requirements for engineering construction

1. The entrance and exit control machines, automatic barriers and other packaging should be intact, the appearance of the material should not be damaged, accessories, spare parts and tools should be complete.

2. Engineering construction wiring standards, wire specifications and models shall meet the relevant requirements of the parking lot engineering design requirements and standard parking lots.

3, carry a complete set of related documents, and information.

Second, engineering construction wiring technical requirements

The wiring of the parking lot system is not only required to be safe and reliable, but also to make the line layout reasonable, neat, and securely installed. Cables shall be installed horizontally or vertically within the building, and shall be protected with a sleeve and securely and securely fixed; 220V power and signal cables shall be laid separately, and they shall not be worn in the same pipe, and the distance shall be greater than 50cm; and all All wiring must be sleeved, PVC pipe and galvanized pipe can be, to avoid rat bite off the line caused by failure; if there is a breakpoint in the middle of the line, the breakpoint must be welded with a soldering iron and do insulation treatment; must be Mark the cables for later installation, commissioning and maintenance.

Bingzhong CAK1000 parking master control board, designed for parking environment, built-in accessories using the United States imported Lattice chip technology, Lattice is today's cutting-edge electronic application technology, its high operating frequency, anti-interference ability, large-scale integration, performance It is stable and has strong computing ability. It has applied advanced interface protection technology and circuit protection technology and is widely used in large-scale control systems and industrial control fields.

The board adopts SMD chip technology, high-precision components, and mature and reasonable circuit design to reduce the number of discrete devices and use large-scale integrated circuits to ensure the safety and stability of the entire system.

1. The power line entrance gate, entrance and exit control machine needs 220V power supply, adopts three-core shielded cable (RVVP3*1.5), generally receives special line UPS special line power supply, in some cases AC220V power supply can also be accessed nearby, but should be in line with For related specifications, ensure that the ground wire in the AC220V socket in the system is grounded.

2. Network cable (control machine - controller or controller - computer)

Parking network can be divided into: 485 communication, TCP / IP communication, RS422 communication, etc. 485 network cable must use shielded twisted pair RVVSP2 * 0.5, 485 bus length, in theory, can reach 1200 meters, it is recommended not to exceed 1000 meters. If more than please use 485HUB or repeater to improve the communication environment. In order to ensure the stability of communication, connect the resistance at the end of the communication line, or connect all the shielding layers together, and the end can be suspended or connected to the ground according to the situation. The 485 network must be a bus type structure that does not allow full or partial star configuration. The TCP/IP network cable can be selected from Category 5 unshielded twisted pair cables. The distance from the controller to the switch or HUB is less than 100 meters.

1. Long distance reader signal lines (reader-controller): The reader signal line uses a four-core shielded cable (RVVP4*0.5).

2. Button line (management room button - barrier): The button line uses a four-core shielded cable (RVVP4*0.5).

3. Talkback Line (Talkback Host - Intercom Ext.): Two-core shielded cable (RVVP2*0.5) is used for the talkback line. The talkback line should be kept away from strong electricity and electromagnetic interference.

4. Display signal line (display screen-controller): The signal line adopts two-core shielded wire: RVVP2*0.5. In order to make the signal wire undisturbed, it should be laid separately from the power wire when laying.

5, control line (barrier - control machine): standard parking control line with four-core shielded cable (RVVP4 * 0.5), simple parking (MAC board) with two-core shielded cable (RVVP2 * 0.5), according to the specific circumstances of parking Field type will be determined.

6. Video cable (camera-control room computer): The video cable uses the SYV75-5 video cable. Do not connect it with other strong power systems. It should keep a distance of 500mm.

III. Technical Requirements for Construction Construction Pipes (Slots)

The line pipe (slot) has two types of open and dark lines. The open line requires horizontal and vertical, neat appearance. Dark pipe requires short, smooth, and elbows. Fixation of line pipe (slot), line pipe (slot) should be fixed at every corner or linear distance more than 1.5 meters. In the vertical nozzle that does not enter the box (box), after the wire is pierced, the nozzle should be sealed. In the access control wiring, the utilization of the diameter of the straight pipe should be 50%~60%, and the utilization of the diameter of the curved pipe should be 40%~50%. If special conditions need to be adjusted during the construction process, they must be approved by the company's leaders and customers before they can be constructed.

Fourth, equipment installation technical requirements

1. The distance between the entrance and exit control machines and the automatic barrier gate control distance from the corresponding barriers shall not be less than three meters (the exit and entrance shall be the same).

The equipment should be perpendicular to the level of the ground, with an inclination of no more than 1°.

The bottom of the box is in close contact with the ground, and the gap is sealed with cement.

The box should not exceed the lane line, minimum 5 cm from the edge of the lane. -

The equipment should be fixed firmly, there should be no shaking, and the equipment should not shift or loosen while resisting 100kg/s momentum.

The entrance control machine should be installed on the left side of the forward direction of the vehicle and the driver read the card from the left window of the vehicle.

2, the display screen should be perpendicular to the level of the ground, the angle of inclination is not more than 1 °. Fixed to the driver's easy-to-see and easy-reverse position.

3. Barrier Control Buttons Barrier control buttons are installed at places where people can easily operate. The specific conditions are based on the site.

Fifth, the technical requirements of the coil 1, coil material: standard Φ0.75mm high temperature tinning line.

2. There can not be a large amount of metal in the range of 50 centimeters around, such as manhole cover, rain gutter cover plate and so on.

3. There must be no more than 220V power supply lines within a 1 meter radius.

4. When making multiple coils, the distance between the coil and the coil should be more than 2 meters, otherwise it will interfere with each other.

5, standard 3 meters wide road, the size of the floor coil is 2 meters long and 1 meter wide, corners do 45 degrees, 20 centimeters long cut angle. As shown below:

6. The distance between the coil and the side of the road is about 50 centimeters, and the coil is vertically superimposed on the circumference of 3-8 turns. The total length is 30-40 meters.

7. The laying line cutting parameters: width 3-5mm, depth 40-50mm, depth and width should be uniform, it should try to avoid the situation of deep and sudden, wide and narrow.

8. The coil should be in the same balance position as the barrier or the controller.

9. The two wires drawn from the coil should be twisted with a density of no less than 50 knots per meter. Untwisted output leads will cause interference. The output lead length should generally not exceed 5 meters. Since the sensitivity of the detection coil decreases as the length of the lead increases, the length of the lead cable must be as short as possible.

Sixth, safety island technical requirements

A circular concrete pier is built on the road, commonly known as a safety island. The safety island mainly plays the role of placing equipment and preventing vehicles from hitting the equipment. If the equipment is installed on the roadside due to the width of the road, it should be installed on the side of the road. Safety island construction precautions:

1. If the size of the foundation to be installed on the equipment should be more than 10cm larger than the actual size of the equipment, prevent the expansion screw from bursting the foundation when fixing the equipment.

System Check Test 2. The safety island should be about 10cm-15cm above the ground.

3. If the ground on which the equipment is installed is a cement foundation, the foundation may be laid directly on the ground, but where the laying is done, a steel bar (Φ20 or more) should be punched every 25 cm in a star shape, and the steel bar should penetrate the ground not less than 5 cm. No less than 5 cm exposed.

4. If the ground on which the equipment is installed is an asphalt foundation, the foundation can be laid directly on the ground, but where the laying is done, a steel bar (Φ20 or more) should be punched every 25 cm in a star shape, and the steel bar should penetrate the ground not less than 20 cm. No less than 5 cm exposed.

VII. System Check and Test 1. Check before installation: Before installing the equipment, it is necessary to verify the installation contract with the type and quantity of equipment in advance and determine the equipment from the warehouse after confirming the error. After the equipment is taken out of the warehouse, it is necessary to test all the equipment one by one to check whether the equipment is normal and to avoid trouble during installation.